Documentation5 min read

New Construction IT Design: Pre-Construction Checklist

A reference checklist for project managers, GCs, and facility owners to ensure IT infrastructure is properly scoped and coordinated before construction begins.

Published February 14, 2026
New ConstructionIT DesignChecklistProject Management

Why IT Planning Starts at Design

IT infrastructure decisions made during design — conduit routing, MDF/IDF room sizing, power and cooling requirements — are far less expensive to change on paper than after walls are closed. IDENETY recommends engaging your IT design team during schematic design at the latest.

Pre-Construction IT Checklist

Telecommunications Rooms

  • MDF/IDF room locations identified and sized per TIA-942 guidelines
  • Dedicated 20A circuits for each telecom room confirmed with electrical
  • Cooling capacity confirmed (minimum 1 ton per 100 sq ft of active equipment)
  • Raised floor or cable management pathway designed

Structured Cabling

  • Horizontal cabling pathway (conduit or J-hooks) coordinated with MEP
  • Cable tray routing confirmed above ceiling
  • Outlet locations confirmed against furniture/workstation layout
  • Backbone pathway between MDF and IDFs confirmed

Wireless Infrastructure

  • AP locations identified in architectural drawings
  • Conduit sleeves for AP drops included in rough-in scope
  • ERRCS/DAS requirements assessed and included if applicable

Security & Access Control

  • Camera locations coordinated with security consultant
  • Access control door hardware locations confirmed
  • Power over Ethernet (PoE) budget confirmed for security devices